EV Charging Installation The Hospice of St Francis, Hertfordshire

See what is possible for your site

We ran cables 50 metres beneath the hospice grounds using horizontal directional drilling, crossing under the main entrance and visitor gardens without a single trench. Five 22kW Easee chargers now serve staff, visitors, and the public. £4,250 in OZEV grant funding secured.

Sensitive SitesHDD/Trenchless DrillingCivils/GroundworksMaintenance & SupportVisitor ChargingElectrical UpgradesGrant FundedLoad Balancing
Five Easee EV chargers installed outside the Spring Centre at The Hospice of St Francis, Berkhamsted with EV parking signage
£4,250 GRANT SECURED
5 Easee CHARGERS
22kW CHARGING SPEED
50 Metres HDD RUN
01

Project details

The Hospice of St Francis provides end-of-life care in Berkhamsted, Hertfordshire. The team wanted EV charging for staff, visitors, and the public, but any installation had to respect the peaceful environment. Here is a snapshot of what we delivered.

Property TypeHospice / Healthcare Facility
LocationBerkhamsted, Hertfordshire
Chargers Installed5 x Easee Home 22kW
Install MethodHorizontal Directional Drilling (50m)
Drilling DepthApproximately 2 metres
Base Type5 x Pre-fabricated Concrete (100kg each)
ElectricalNew Fuse Board with Expansion Capacity
Funding Secured£4,250 (OZEV Grant)
Access TypePublic, Staff, and Visitor Charging
ClientThe Hospice of St Francis
Main entrance of The Hospice of St Francis in Berkhamsted featuring blue sculpture of a human head with open hand in landscaped gardens

The Hospice of St Francis came to us after other installers had struggled with the site. Previous quotes proposed traditional trenching that would have disrupted the grounds for weeks. The hospice needed an installer who could deliver the infrastructure without affecting patients, families, or daily operations. The team had clear goals: charging for staff, visitors, and the public, with revenue flowing back to support their charitable work. They also wanted the charging area to look like a deliberate improvement, not an afterthought bolted onto the car park.

02

The challenge

Horizontal directional drilling crew working on the grounds at The Hospice of St Francis in Berkhamsted, Hertfordshire

A Sensitive Environment Requiring Zero Surface Disruption

The Hospice of St Francis provides end-of-life care in a carefully maintained, peaceful setting. Patients, families, and staff depend on an atmosphere of calm and dignity. Any construction work had to respect this environment completely. Traditional trenching would have torn up pathways, closed sections of the grounds, and created noise and disruption for weeks. The hospice operates 24 hours a day, with visitors arriving at all hours. The installation could not affect the experience of anyone using the facility.

Horizontal directional drilling rig installing underground cable ducts at The Hospice of St Francis, Berkhamsted

50 Metres of Cable Route Across Gardens and Entrance

The main electrical intake was located inside the building, 50 metres from the proposed charging location. The cable route had to cross the main entrance, visitor gardens, and landscaped areas. Open trenching would have left visible scarring across the site and required weeks of reinstatement. Running cables along the surface or through the building interior was not acceptable. The grounds at The Hospice of St Francis are part of the care environment, and any damage would have been noticed immediately. A different approach was needed.

Operator running horizontal directional drilling rig to install underground cable ducts at Berkhamsted hospice grounds

Maintaining 24/7 Access During Installation

The hospice operates around the clock. Deliveries, emergency services, and visitors need uninterrupted access at all times. The main entrance could not be closed or blocked during the installation. Any work causing noise or creating obstructions would have affected patients and families during an already difficult time. The installation team had to work around the hospice's operations without requiring any changes to their schedule. This meant careful planning and an installation method that would not close roads, paths, or parking areas.

I am thrilled with the service and results EV-ON provided for our hospice. From the initial consultation to the final installation, their team showed remarkable professionalism, efficient project management, and clear communication throughout. The speed and attention to detail with which they executed the project were truly impressive. The finished product exceeded our expectations, blending with our surroundings and providing a convenient and sustainable charging solution. I highly commend EV-ON for their expertise, dedication, and outstanding service.
George SearsThe Hospice of St Francis
03

Our solution

Charger pedestals on concrete bases with orange safety barriers during EV charging installation at The Hospice of St Francis, Berkhamsted

Horizontal Directional Drilling Beneath the Grounds

We used Horizontal Directional Drilling to install service ducts beneath the grounds without breaking the surface. A specialist HDD rig was positioned at the starting point, with the exit pit located 50 metres away at the charging location. The process began with a pilot bore, a small-diameter hole drilled along the planned route using a steerable drill head. A specialised scanner tracked the drill head in real time, providing position and direction data at approximately 2 metres below ground level. Once the pilot bore reached the exit point, we attached a reamer and pulled it back through the bore, widening the hole and installing multiple cable ducts in one pass. The entire 50-metre underground run was completed in a single day.

GRP electrical cabinet flanked by Easee charger pedestals at The Hospice of St Francis healthcare facility in Hertfordshire

Future-Ready Electrical Infrastructure

We installed a new fuse board housed in a GRP enclosure at the charging location. The enclosure protects the electrical equipment from weather while keeping it accessible for maintenance. The fuse board was specified with expanded capacity built in from the start. The hospice can add more chargers in the future without needing further groundworks or panel upgrades. We also installed ducting between the five charger bases. If cables ever need replacing or upgrading, they can be pulled through without excavation. This forward-thinking approach means the infrastructure will serve the hospice for years to come.

Completed Easee EV charger pedestals in landscaped parking area at The Hospice of St Francis, Berkhamsted

Landscaped Charging Area with Public Access

We positioned five pre-fabricated concrete bases, each weighing 100kg, for pedestal alignment across the charging bays. Each Easee 22kW charger was mounted, tested, and connected to our management platform. We also installed new lamp post lighting to improve visibility and safety in the charging area. After installation, we landscaped the entire area with new borders, planting, and surface finishes. The result is a professional, welcoming amenity that matches the care the hospice puts into the rest of its grounds. The chargers are open to the public, not just staff and visitors. Drivers pay per kWh through the integrated payment platform, generating revenue that flows back to support the hospice's work.

04

The results

Project outcomes

The Hospice of St Francis now has five EV charging points without any visible impact on the grounds. The 50-metre cable run sits approximately 2 metres underground, crossing beneath the main entrance, visitor gardens, and landscaped areas without a single trench or surface cut. The drilling process saved multiple days of disruption and avoided closure of the main entrance. Patients, families, and staff saw no interruption to their daily routine.

The landscaped charging area has transformed the space into a welcoming amenity. New borders, planting, lamp post lighting, and surface finishes mean the chargers sit within a setting that reflects the hospice's attention to care. What was a plain car park area is now an attractive, purpose-built facility that the hospice is proud to show visitors.

The £4,250 OZEV grant reduced costs significantly. The electrical infrastructure is built to support additional chargers as EV adoption grows, with ducting in place for future cable upgrades. The hospice has opened the chargers to the public, generating ongoing revenue to support their charitable work. Over time, the chargers will pay for themselves and continue to benefit the organisation for years to come. Our team monitors all five units remotely and handles any maintenance issues directly.

Services provided

  • Site survey and utility detection
  • Geological assessment for HDD route planning
  • Horizontal Directional Drilling (50m underground run)
  • Real-time GPS tracking during drilling
  • GRP enclosure and fuse board installation
  • Supply and installation of 5 x 22kW Easee chargers
  • Pedestal mounting on pre-fabricated concrete bases
  • Ducting between bases for future cable replacement
  • Lamp post lighting installation
  • Full landscaping and surface finishes
  • Management platform integration and payment setup
  • OZEV Infrastructure Grant application (£4,250 secured)
  • Ongoing remote monitoring and maintenance

More projects we have delivered.

Every project surveyed, installed, commissioned and monitored by our own team. Grants secured and managed end to end.

View all case studies

Become our next
success story.

Tell us about your site. We survey, explain your options, and give you a clear quote with no obligation.

Enter your details below and one of our solar experts will be in touch.

We reply within one working day. No marketing emails.